South Shore Regional Vocational

Technical High School

Project Overview

Since starting the feasibility and completing the first submission to the MSBA, the options of building layout and enrollment continued to be narrowed down from the original 30 versions, and the goal was to have the one final option selected in February.

At the SBC meeting on February 22, 2024 the School Building Committee formally voted on proceeding with submitting the Preferred Schematic Report on February 29, with the selected option NC2.0 with an enrollment of 900 students and that was submitted on February 29 to the MSBA.

 

The project is now in Schematic Design, with the next submission due to the MSBA on August 29, 2024. Below are some of the most recent renderings for the proposed  new school.

The project team evaluated the layout on the site and determined the best option to accomodate the school activities while working with the restraints of the site such as wetlands, traffic patterns, parking and athletic fields was Option 1. 

Project Background

On or about June 2, 2021, the Owner submitted a Statement of Interest (Attachment A) to the MSBA for South Shore Regional Vocational Technical High School. The MSBA is an independent public authority that administers and funds a program for grants to eligible cities, towns, and regional school districts for school construction and renovation projects. The MSBA’s grant program is discretionary, and no city, town, or regional school district has any entitlement to any funds from the MSBA. At the October 26, 2022 Board of Directors meeting, the MSBA voted to issue an invitation to the Owner to conduct a feasibility study for this Statement of Interest to identify and study possible solutions and, through a collaborative process with the MSBA, reach a mutually-agreed upon solution.

Project Timeline and Status

JUNE 2, 2021

South Shore Tech Submits a Statement of Interest to the MSBA

OCTOBER 26, 2022

MSBA Invites South Shore Tech Into the Feasibility Study Program

February 6, 2023

Leftfield is appointed as the OPM

MAY 2023

South Shore Tech Selects DRA as Their Designer for the Project

MAY 2023

The Feasibility Study for South Shore Tech Starts

OCTOBER 2023

PDP is Submitted to the MSBA

FEBRUARY 2024

PSR is submitted to the MSBA

MAY 2024

South Shore Tech Selects Suffolk Construction as their CM

Shortcuts

MSBA WEBSITE

Click here for more information about funding and protocols of capital improvement projects in the Commonwealth’s public schools

GLOSSARY OF TERMS

Click here for a reference guide to clarify context and meaning to common terms used in the building process for public projects

PROJECT UPDATES

South Shore Tech’s School Building Committee voted at the December 14th Meeting to proceed with CM-at-Risk procurement for the project. The process was started by submitting a request for approval to the Inspector General’s office and receiving the approval on March 8, 2024. Public advertising for CM firms Pre-Qualifications (RFQ) was done on March 6 with responses due on March 27, followed by Request for Proposals (RFP) from the qualified firms and the interview process on May 9th & 10th. During deliberations on May 10th, Suffolk Construction was ranked as the #1 firm and contract negotiations were started.

While evaluating the options for enrollment and building, the project team has issued estimated Tax Impact Analysis for the different districts. This analysis is provied for comparison purposes ONLY and it will be updated and finalized at the end of schematic design.

A message from Superintendent Tom Hickey
To view the presentation without narration, click here

South Shore Tech, the selected designer, Drummey Rosane Anderson, Inc. (DRA), and the project team are in the midldle stages of the Feasibility Study. The first portion was spent on educational visioning and space planning, and  the first submission to the MSBA known as the PDP (Preliminary Design Program), was submitted in October, 2023. The next step in the feasibility study was the PSR (Preferred Schematic Report) submission, which was submitted in April 2024. After the PSR Submission the project went in front of the MSBA Board of Directors on April 26, 2024 and was formally voted through to proceed into Schematic Design. Following a more in-depth design and site development, the next submission that goes to the MSBA will be the Schematic Design Submission on August 29, 2024.

UPCOMING EVENTS

MOST RECENT EVENTS

Whitman Forum

June 8, 2024

QUESTIONS

CONTACT US
FAQs